Keeping projects on track and on time

  • Posted: Monday, November 23, 2020, 7:38 am
Building 12-34 is due for demolition in FY2020

Building 12-34 is due for demolition in FY2020

Pantex and Y-12 have valiantly continued vital work throughout the COVID-19 response. A part of that work is to ensure projects remain on track and on time. As of June 29, Pantex Projects had the remaining 22 projects released to return-to-work, bringing the total to 68 projects they are working on. The phased return-to-work focused on the safe return of Pantex subcontractors, beginning with priority projects first. Some of those projects included bay and cell fire system upgrades, roof asset management and a hoist installation.

To keep things moving with health and safety in mind, especially when working with off-site contractors, requirements such as approving COVID-19 safety plans were put into place and contractors were required to follow Pantex COVID-19 requirements. Even in the early stages of the pandemic protocols, here’s an example of how Pantex Projects continued their mission:

Demolition projects at Pantex are planned for many years in the future, and are bringing new interest and contractors to Pantex to perform work. Buildings 12-14 and 12-34 are two of several demolition projects on National Nuclear Security Administration’s 2020 Make It Happen List. These two demolition projects recently progressed through planning and design phases to the contractor bid phase and were the last of the 2020 demolition projects to go out for bid.

“The consequences of moving on with the bid phase without a walk down is that bidders do not submit bids or the bids are not accurate for the tasks to be performed,” said Marlin Conner, project manager. “The walk downs are a crucial step in the procurement process to facilitate competitive and fair bids.”

On May 20, representatives from 18 companies were at Pantex for the walk downs. Normally, contractors attend a pre-bid walk down before bids are submitted to see the site conditions, validate drawings provided with the Request for Proposal, and evaluate the scope for tasks that may be more or less complex than understood from the documents provided. Just before the walk down was scheduled, the plant implemented the COVID-19 Containment Phase, which resulted in delay.

The integrated project team was determined to continue the project’s momentum, and with the help of many Pantex team members, were able to overcome the obstacles and safely conduct the walk downs. In order to ensure the safety of people and facilities, each contractor employee was cleared by Medical before coming to Pantex, and all participants wore face masks. After thoroughly searching vehicles and screening people, Security cocooned the group through the security gates to eliminate the use of ARGUS stations and reduce surfaces touched by both Plant and contractor personnel. Groups were kept small and rotated through the facilities.

“At the end of the day, the walk downs were conducted just as planned due to the diligence and determination of the team,” Conner said.

They ended up with six bids, which is still an impressive amount, even outside of the pandemic.


Building 12-14 is due for demolition in FY2020